With both airlock doors open, the 10–15 Pa that usually separates two adjacent grades is gone within seconds.
That is why cleanroom airlocks get door interlocks. It is also why EHS asks the first question at every design review: what happens in a fire? A door that will not open is a life-safety problem, however good it is for the cascade, so the specification has to cover the release as well as the lock.
What we put in that specification:
- One door open, or not latched, holds the other locked, with a short delay after closing if the airlock needs time to recover.
- A status lamp on both sides of each door, so nobody pulls a locked door until something breaks.
- A fire alarm signal drops every interlock in the zone.
- An emergency release at each door, and fail-safe locks that open on loss of power.
- Every use of the override logged and alarmed on the BMS, so QA knows when the cascade was broken and for how long.
- The override proven at FAT on the control panel, again at OQ in the room, then on a set interval.
Testing the release in a qualified room means deliberately losing the pressure step for a few minutes. Plan that slot with QA in advance rather than fitting it in on the day.