1 ppb of ammonia is about 0.70 µg/m³. The same 1 ppb of hydrogen chloride is about 1.49 µg/m³.
Airborne molecular contamination is gas and vapour: acids, bases, organics, dopants. The HEPA and ULPA filters that hold a fab to its ISO class are rated on particles, and an ammonia molecule goes straight through them. AMC needs its own specification, its own filter stages and its own measurements.
The specification is where it tends to go loose. Process teams usually think in ppb by volume, because that is what their monitors report. ISO 14644-8 classifies chemical air cleanliness by mass concentration in g/m³, and chemical filter suppliers quote in either. The conversion runs through molecular weight: µg/m³ = ppb × MW / 24.45, at 25 °C and 1 atm. A single "1 ppb" limit for acids is therefore a different mass for every acid in the group, and the adsorbent bed is sized on mass.
A URS line for AMC that a supplier cannot misread has three parts: the compound or named group, the unit with its reference temperature, and the sampling method that will prove it. Leave any of them out and the filter supplier makes the choice.
At Humiley, AMC control sits in the semiconductor scope next to multi-stage HEPA/ULPA filtration and ±2% RH micro-environments.
Which unit does your process team write AMC limits in?