People still write "Class 100" into URS documents, more than 25 years after the standard that defined it was cancelled.
FED-STD-209E was cancelled in 2001 and replaced by ISO 14644-1. Its classes counted particles of 0.5 µm and larger per cubic foot. Class 100 meant 100 per cubic foot.
ISO 14644-1 counts per cubic metre, at several particle sizes. One cubic metre is about 35.3 cubic feet, so 100 per cubic foot is roughly 3,530 per cubic metre, which is why ISO 5 sits at 3,520 at 0.5 µm.
The FDA's 2004 aseptic guidance still prints both names side by side: Class 100 is ISO 5, Class 10,000 is ISO 7, Class 100,000 is ISO 8, all measured in operation. That table is where most of the old names survive.
The mapping is clean only at 0.5 µm and only when the occupancy state is stated. "Class 10,000" says nothing about at rest versus in operation, and nothing about the EU grade. Written into a URS for an EU market, it leaves the designer to guess between a Grade B background and a Grade C room.
Our suggestion: write the ISO class, the particle size, the state and the EU grade where it applies. "ISO 7 in operation, Grade B" leaves nothing to guess.