Diffuser type and mixing in a Grade C room

  • Life Sciences
  • 1 min read

In a Grade C room at 20 air changes an hour, perfect mixing gives a 100:1 recovery time of about 14 minutes.

The supply terminal decides how far a real room falls short, because mixed-flow rooms clean themselves by dilution. For ideal mixing the 100:1 recovery time is ln(100) divided by the air change rate, so 4.6 / 20 of an hour, or 13.8 minutes. A corner the supply air only half reaches can behave like a room at 10 air changes, and the same sum gives about 28 minutes.

Swirl diffusers come closest to the ideal. They throw air out radially and pull a lot of room air into the jet, which evens out concentrations, at the cost of some turbulence at head height and more noise at high flow. Perforated face plates induce less and tend to leave slower spots between terminals, most of all where low-level returns are far apart.

Take the diffuser plate away and a HEPA terminal sends a low-velocity plume straight down. Over a critical bench that can be the right choice, because directly underneath is very clean. Repeated along a whole Grade C corridor, the plumes do not spread far and the corners catch up slowly.

This is why the probe position in the ISO 14644-3 recovery test matters. A probe under a terminal reports the best figure in the room. Place it where the smoke study shows the air arriving last.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Industries

Related

More on this subject

ISO Class 1 vs ISO 5: counting at 0.1 µm

ISO Class 1 allows 10 particles of 0.1 µm and larger per cubic metre; ISO 5 allows 100,000 at that size. At that level the installed leak scan must prove frames and grid, not just the U15 filter, single-digit counts need large sample volumes, and airborne molecular contamination needs its own sampling plan.

InsightRead

EN 1822 ULPA classes add a nine each above H14: U15 99.9995%, U16 99.99995%, U17 99.999995% at MPPS. Semiconductor ISO Class 1 to 3 spaces need them. A pharma Grade A zone at ISO 5 rarely does, because people and seal leaks drive its counts; H14 with a sound seal usually carries it.

InsightRead

What ends the life of a HEPA filter

EU GMP Annex 1 (2022) asks for an integrity test of final filters at requalification and puts no age on the filter. A terminal HEPA is replaced when a leak cannot be repaired within site limits, when pressure drop reaches the manufacturer's final value, or after damage or wetting. On glass-fibre media, dust loading alone does not lower efficiency.

InsightRead