When a turnover package is thin, IQ becomes the place where construction gets finished.
The IQ protocol asks for evidence the package should already hold.
You can usually tell within ten minutes of opening the binder: drawings marked "for construction", not as-built; a punch list with a "remarks" column instead of a closed date; calibration certificates for half the instruments. The IQ team then spends its first week chasing documents.
The contents we expect before a package crosses from construction into qualification:
- A marked-up boundary. Which AHU, which rooms, which instruments, drawn on the layout, so nobody argues later about what was handed over.
- The punch list, split in two. Items that block qualification, all closed and signed. Cosmetic items listed separately with an owner.
- Commissioning and balancing results. Airflows per terminal, room pressures, the test and balance report, signed.
- As-built drawings that match a walkdown done by someone other than the installer.
- The evidence behind the equipment. Calibration certificates for every instrument in the boundary, and the equipment file from manufacture: material certificates, FAT report, O&M manual.
If any of the five is missing, the package goes back.
Humiley manages construction into qualification as one of four explicit handovers, so IQ starts from a verified installation.