A cooling tower cannot cool water below the wet-bulb temperature of the air it pulls through the fill.
Leaving water is wet-bulb plus approach. With 28 °C as an illustrative tropical design wet-bulb and a 3–4 K approach, condenser water returns to the chiller at 31–32 °C. The same tower at a site designed for 20 °C wet-bulb would deliver 23–24 °C.
Condenser water temperature sets the chiller's lift, and lift sets compressor power. A common rule of thumb is 2–3% more compressor power per kelvin of condenser water; the chiller's own part-load data gives the real figure. Take a chiller drawing 180 kW at design. One extra kelvin of approach at 2.5% is about 4.5 kW, and over 8,000 running hours a year that comes to about 36,000 kWh. In the tropics the wet-bulb stays high for most of the year, so that penalty has no cool season to hide in.
Buying that kelvin back takes more fill, a larger tower or more fan power. Film fill reaches the closest approach but fouls quickly when water treatment slips, and once it fouls its approach opens up. Splash fill tolerates poor water and gives up some approach from the start. On a site where water treatment is patchy, the design approach of a film-fill tower may never be seen in operation.
Has anyone measured the kW-per-kelvin figure on their own chillers instead of using a rule of thumb?
Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)
Topics