Where the fresh-air quantity actually comes from

  • News
  • 1 min read

Through a 100 cm² gap at 15 Pa, a door passes about 110 m³/h. Whether that costs fresh air depends on where the door sits.

The orifice equation gives the flow: Q = Cd·A·√(2Δp/ρ). With Cd 0.61 and air at 1.2 kg/m³, the ideal jet velocity is 5 m/s, the mean velocity over the gap about 3 m/s, and the flow about 110 m³/h.

A door between two rooms on the same AHU moves that air next door, where the neighbour's return grille picks it up and sends it back to the unit. It costs no fresh air. A door from the suite to a corridor on another system, a plant room or outdoors is different. That air leaves the AHU's circuit, and the fresh-air intake has to replace it, along with pass-box and joint leakage on the boundary.

Take a suite with twenty doors, four of them on the boundary. Counting every door gives 2,200 m³/h of leakage to make up. Counting the boundary gives 440 m³/h. In the tropics each of those cubic metres arrives wet and has to be dried at peak dew point, so the error goes straight into coil size.

Fresh air has to replace everything that leaves the circuit, extract plus boundary leakage, and it also has to meet the occupant minimum where ASHRAE 62.1 or a local code applies. The larger of the two sets the flow.

At commissioning, measure supply minus return for the whole suite and compare it with the boundary leakage the design assumed.