The load calculation assumed four operators in the filling room; the aseptic process simulation qualified six.
Both numbers look fine in their own documents. The HVAC design sized airflow, cooling and recovery time for four gowned people, because people are the largest particle source in the room and a real share of its sensible and latent load. The APS, following EU GMP Annex 1, was run with the maximum number of personnel production expected to need, and that maximum then becomes the limit written into procedure.
Side by side, the room is now allowed to run with six people while the air handling was designed for four. In-operation particle counts may still pass on most days. The margin meant to protect the room during an intervention has been spent on headcount.
The reverse happens too. A design for eight and an APS for four leaves capacity the site paid for and cannot use without another simulation.
One number per room solves it: maximum occupancy written in the URS, then carried into the load calculation, the room data sheet, the APS protocol and the gowning and entry SOP. When production wants to change it, all of those documents change together.
Humiley writes the URS and validation strategy in parallel with the design, which is where that number should first appear.