On most transfer plans the registration batch date is the one line nobody is allowed to move.
An assessor reads what stands behind the batches made on that date. By the time the first one is dispensed, five things should be true, each with a signed document.
- Equipment, utilities and rooms are qualified: IQ and OQ reports approved, laboratory instruments included.
- Analytical procedures are transferred and the transfer report is approved.
- Material specifications are approved, and so are the suppliers.
- The master batch record is approved and issued. A draft with handwritten changes is a development record.
- Operators are trained on this process, with records.
WHO's technology transfer guideline (TRS 1044, Annex 4) says the two sites should jointly verify IQ and OQ data, room qualification and cleaning validation. EU GMP Annex 15 (2015) says equipment used for process validation should be qualified and test methods validated, that the batches should be made by trained personnel using approved documentation, and that suppliers of critical materials should be qualified first, or the gap justified by risk. Both are written for transfer and validation batches; the rest of the list, and applying it to registration batches, is our reading.
On a new site the date is really set by construction, because qualification cannot start from an open punch list.