Most nights the pressure sensor in the "mothballed" room still alarms, and its PM tasks still print every month.
A room taken out of use without paperwork stays in every system that knew about it. EU GMP Annex 15 (2015) has no section on decommissioning. Its glossary defines lifecycle as running from initial development or use through to discontinuation of use, and its change control section says written procedures should describe the actions to be taken for a planned change to equipment or premises. Taking a room out of service is such a change, and a change record that covers it shows the following.
- An assessment of the neighbours. A room that drops out of the cascade changes the pressures and airflows of the rooms around it.
- Final records closed and archived: logbooks, the last calibration and requalification, and the monitoring data, with the place they are kept. The 2011 text of EU GMP Chapter 4 says it should be clearly defined which record is related to each manufacturing activity and where this record is located.
- Utilities isolated and tagged, ducts capped, and the drawings marked up.
- The asset register, PM plan and calibration schedule updated, so nobody is sent to maintain a dead room.
- Monitoring points and alarms formally retired in the BMS or EMS, with the date, and not merely inhibited.