Direct-on-line, soft starter or VFD for AHU fans

  • News
  • 1 min read

A soft starter brings an AHU fan up to speed gently and then leaves it at one speed for the rest of its life.

Direct-on-line is cheaper still and the simplest to maintain, at the price of an inrush the transformer, generator and upstream breaker all have to carry. A soft starter ramps the voltage instead and cuts the starting current, typically to around 3–4 times full load depending on the setting and the load. Once the fan is up to speed it is bypassed, and the motor runs flat out. After the bypass closes it adds no harmonics.

A VFD starts the motor at close to full-load current and then controls its speed. On a cleanroom supply fan that matters more than the start: as the filters load, the drive speeds up to hold design airflow, and the rooms keep their air change rate and pressures. The price is harmonics. A 6-pulse drive draws current at a THDi of roughly 65–75% without a DC choke and 35–42% with one, and several drives on one board raise the voltage distortion for everything else it feeds.

For a GMP supply or return fan we choose the VFD, with the DC choke written into the specification and active filtering decided from a harmonic study against IEEE 519-2022. A soft starter still suits a fixed-duty fan whose airflow nobody will need to trim.

Related

More on this subject