1/16 inch per foot is the smallest gravity slope ASME BPE designates for drainable process lines.
That is about 5 mm per metre, and easy to lose on site. On a 10 m run of clean steam line, the whole fall is about 52 mm. With hangers about 1 m apart, each one sits only 5 mm or so below the last. Set one of them 5 mm high and the metre leading to it is practically flat; at 2 m spacing the same error halves the fall on that span. In a line that must drain before steaming, that span holds condensate, the steam-in-place cycle misses temperature there, and the drainability check fails.
The steeper designations, 1/8 in/ft and 1/4 in/ft, forgive more but need height the ceiling void rarely has. So the lowest slope gets specified, and then hangers are set from the steelwork before anyone has surveyed the line.
A safer sequence starts with surveyed high and low points. Set out the fall between them, fix the hangers to that line, then check the installed slope span by span with a level or laser before the insulation goes on, and write each reading down. After lagging, a sag usually shows up first as a failed drainability test.
We would rather find those readings in the turnover package than a note saying "sloped per drawing". Clean utilities are part of Humiley's engineering scope, and we hand systems to qualification package by package, each with its own evidence.
How is slope recorded in the last turnover package you accepted?