First start of a new AHU: the site sequence

  • Manufacturing & Distribution
  • 1 min read

The first minute a new AHU fan runs decides whether the fan section gets reworked on site.

Most first-start damage comes from something left inside or left bolted: a transit bracket still locking the fan base, a closed fire damper, a spanner on the floor of the fan section. The sequence is short.

  1. Clear the fan section and remove the transit fixings so the fan base floats on its anti-vibration mounts. Open the dampers in the air path, confirm the filters are fitted and the drain trap is primed.
  2. Test the motor insulation with the drive disconnected, then bump the fan for a second or two and watch the direction. A backward-curved fan running in reverse still pushes air the right way, at a fraction of the flow, so airflow alone proves nothing. (EC fans fix their own rotation; check the wiring and the control signal.)
  3. Run at low speed for a few minutes. Listen for rubbing at the inlet cone and look at the flexible connections.
  4. Read motor current on each phase, vibration and bearing temperature, and write them down with the speed.
  5. Ramp to duty in stages and record the static pressure across each section. That profile is the baseline for every later filter and coil reading.

Our AHUs are FAT-tested and witnessed before they ship. Transport and installation come after the FAT, so the site start gets its own record. Where the manufacturer's start-up instructions differ from this list, follow them.

Related

More on this subject

Five things a package needs before IQ

IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.

InsightRead

EN 1886 class L2 allows an AHU casing 0.44 l/s per m² of leakage at −400 Pa. On a witnessed FAT, casing leakage, fan airflow at design static pressure, filter bypass and the control panel are checked against the approved specification, and both engineers sign the sheet that goes into the equipment file.

InsightRead

An ISO 9001 certificate shows that a supplier's quality management system was audited within a stated scope. It does not show that the equipment or service you bought meets your requirement. Supplier qualification assesses what you buy, against your URS, to a depth set by risk: questionnaire, audit or factory hold points.