Skip to content

Project Management Consultancy

EPCM governance: four tools, used every week

  • Project Management Consultancy
  • 1 min read

A project that reports progress as "percent complete" is reporting an opinion.

Earned value turns it into a measurement. Planned value, earned value and actual cost give two ratios: SPI = EV / PV and CPI = EV / AC. Below 1.0 on either is a signal. Below 1.0 for three months running is a conversation the owner should already have had.

Earned value is one of four governance tools we run on EPCM projects:

  1. Stage gates from concept to PQ. Each gate has a defined deliverable list and a go/no-go decision, so design doesn't drift into construction unresolved.
  2. Earned value, reported monthly alongside schedule, cost and risk.
  3. A live FMEA risk register reviewed weekly. Weekly matters. A risk reviewed quarterly is often reviewed after it has happened.
  4. A RACI that everyone has seen, including the owner's QA team. Many disputes on site are about who was supposed to approve something.

None of this is exotic. It is PMP-aligned project management inside an ISO 9001-aligned QMS. The difference between projects is whether the tools are used every week or produced for the kick-off meeting and filed.

Which of the four is the first to lapse on the projects you've seen?

Related

More on this subject

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.

InsightRead

Grade B at rest: state the equipment condition

Grade B at rest is held to 3,520 particles ≥0.5 µm and 29 ≥5 µm per m³. Annex 1 (2022) defines at rest for GMP grades as HVAC running, main equipment installed and standing by, and no personnel, reached after a clean-up period of under 20 minutes as guidance. The protocol should record that condition.

InsightRead