A good filter in a leaky frame performs like a worse filter, and no efficiency test on the filter itself will show it.
Take a filter stage that passes 5% of particles. Add 2% of the airflow slipping round the frame unfiltered. Downstream you now see almost 7%: close to 40% more particles, from a gap you cannot see with the door shut.
EN 1886 tests exactly this on the AHU casing. The filter cells are blanked off and the air that still gets past the frame is measured. Class F9, the tightest, allows 0.5% of the airflow to bypass. The class names follow the old filter grades: an F9 frame is tight enough for a filter of that grade. Filters themselves are now rated to ISO 16890 (ePM1, ePM2.5, ePM10); the bypass class is about everything around them.
What passes the test is mechanical, not filtration:
A frame rigid enough not to flex under the pressure drop of a loaded filter.
A continuous gasket, compressed evenly, with no joints at the corners.
Clamps that press at the corners and the mid-points, not only at two sides.
Filter rails sealed to the casing, because air finds the rail before it finds the gasket.
Put the EN 1886 filter bypass class on the data sheet and look at the frames during FAT. Every AeroSano unit is FAT-tested and witnessed against the approved specification, which is where a frame that flexes should be found.