16 fins per inch give a cooling coil a fin pitch of about 1.6 mm. On a coil that runs wet most of the year, water fills the gaps.
The pitch is 25.4 mm divided by the fin count. Tight spacing puts more surface into the same face area, so the coil gets smaller for the same duty, the casing shrinks and the price drops a little. On a dry heating coil that trade is usually fine.
A dehumidifying coil in Viet Nam condenses water for most of the year. Water bridges the narrow gaps, the free area falls, pressure drop rises and the fan speeds up to hold airflow. Droplets tear off at the leaving face and carry into the next section or the duct. Dust that would pass a dry coil sticks to wet fins, and a film grows in the middle of the pack where a spray wand from one side does not reach.
At 10 fins per inch the pitch is about 2.5 mm, with 37% fewer fins per row. The duty has to come back through an extra row or a larger face, so the coil costs more and the casing grows. In return, water drains, the pressure drop stays nearer its clean value and a technician can clean through the pack.
Hygienic AHU guidance, including VDI 6022 and EN 13053, addresses coil cleanability; check the minimum spacing in the edition your specification cites. AeroSano AHUs are engineered from the project's own load calculation, so the spacing is priced from the start.