An old AHU leaves a running plant carrying loaded filters, a drain pan that has held water for years and insulation that sheds fibre.
It is the dirtiest thing moving through the building that weekend, and it is easy to plan the new unit in detail and the old one in a single line.
Start with the route. A roof unit may come out by crane in one lift, and then the lift plan, the crane's load chart and the exclusion zone below decide the date as much as production does. A unit in an internal plant room usually cannot leave in one piece. It is cut into sections where it stands, and each section needs a path to the door that avoids corridors serving classified rooms.
Before anything is unbolted, bag the filters in place, drain and wipe the drain pan, and blank every duct opening the unit will leave behind. Cutting casing throws out metal dust and insulation fibre, so the plant room is sealed, held negative to its neighbours with a portable extract unit through a filter, and cleaned before the new unit comes in.
Then the rooms next door. The AHU being removed is off; the ones serving adjacent suites are not, and a plant room door propped open for a trolley can pull a neighbouring corridor out of its cascade. Watch those differentials for the whole job.
We take work from a single AHU replacement in a running facility up to a full greenfield GMP plant.