A room held at 20 °C / 45% RH has a dew point of about 7.7 °C.
Every recirculation coil that serves it is either above that number or quietly below it.
Above it, the coil is dry. Say it is fed chilled water at 12 °C: no fin surface gets cold enough to condense. There is no condensate, no standing water in the drain pan, and nothing for microbes to live on. The water circuit is also warmer, which helps the chiller.
Below it, the coil is wet. Feed the same coil 6 °C water and the fins near the water inlet drop under the dew point. The coil starts pulling moisture out of the room air. That sounds harmless until you notice it is now a second dehumidifier fighting the fresh-air unit's humidity control, often followed by reheat to put the temperature back. And it gives you a drain pan and a trap to keep clean and wet in every plant room.
The dry-coil option is not free. A coil running on 12 °C water has less capacity per row, so it gets deeper or larger, and the site needs a second chilled water temperature, from a separate circuit or a mixing loop. On a small plant that can cost more than it saves.
Where the fresh-air unit already does all the drying, we would rather pay for the bigger coil than own a wet pan in every AHU.