Stack effect and the clean corridor

  • News
  • 1 min read

A stairwell 10 m tall, 10 K warmer or cooler than the building around it, sets up about 4 Pa between its top and bottom.

A door near the top or bottom sees up to half of that against a 10–15 Pa cascade step, and the AHU has no part in it.

The physics is buoyancy. Warm air in a vertical shaft is lighter than the air around it, so the shaft pushes out near the top and draws in near the bottom, with a neutral plane somewhere between. The pressure is gravity times height times the difference in air density. At 10 m and 10 K the density difference is about 0.04 kg/m³, so 9.81 × 10 × 0.04 ≈ 4 Pa.

Stairwells, lift shafts and vertical service risers all behave this way. When one opens onto a clean corridor, the corridor's pressure relative to the shaft changes with the floor, with the weather and with whether the stair door is open. On a lower floor the shaft may draw air out of the corridor; higher up it may push into it. A cascade balanced on a mild afternoon reads a few pascals off another day, and nobody can explain the drift.

Three things help: an airlock or lobby between the shaft and the clean corridor, a shaft that is itself conditioned or pressurised, and pressure sensors referenced to a space that does not move with the shaft.

Humiley designs pressure cascades for multi-storey plants with the shafts drawn in, since the AHU controls cannot see them.

Does your cascade drift with the weather or with the time of day?

Related

More on this subject

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.