Rain can take tropical outdoor air from 32 °C to about 26 °C and leave it holding the same 21 g of water per kg of dry air.
For the coil that treats fresh air, the shower removes part of the sensible duty and none of the latent duty. The cleanroom's own heat, from lights, process equipment, fans and gowned operators, is the same whatever the weather.
The fresh-air side is lopsided even on a dry afternoon. Air at 32 °C and 70% RH cooled to 12 °C saturated drops from about 21 to 8.7 g/kg, and of the roughly 52 kJ removed per kilogram, about 32 kJ condenses water. After the rain the latent share is larger still.
On a single coil that handles fresh and return air together, with its valve on supply or room temperature, this is where humidity gets away. The cooler fresh air lowers the mixed-air temperature, the controller closes the valve to hold setpoint, the coil surface warms, and less water condenses while the same moisture keeps arriving. Room RH creeps up through the afternoon.
With two coils, the fresh-air coil is sized on the peak outdoor dew point and its valve follows leaving dew point, so it stays open when the rain comes. The recirculation coil gets air that is already dry, runs dry or nearly dry, and follows room temperature.
In Viet Nam we treat dehumidification staging and the reheat penalty as primary design decisions.
On your fresh-air units, does the valve follow leaving dew point or supply temperature?