Grade B at rest vs in operation: what changes between the two

  • Life Sciences
  • 1 min read

When Grade B counts creep up during operation, the filters are usually the first suspect. They are often the wrong one.

The standard itself tells you why. At rest, Grade B must meet ISO 5: no more than 3,520 particles ≥ 0.5 µm per m³. In operation the limit becomes 352,000 per m³, which is ISO 7, a hundredfold allowance. The airflow is the same. What changed is that the line started and the operators walked in.

People are the largest particle source in a cleanroom. Skin flakes, fibres and droplets escape at gown closures, cuffs and around the face, and the rate climbs sharply with movement. A still operator and one reaching across a line are very different sources.

What that means in practice:

  1. Size the airflow for the in-operation state, with the number of people the process really needs, not the headcount at the design review.
  2. Set the clean-up period. After operations stop, the room should get back to its at-rest limits within a period fixed during qualification (Annex 1 guidance: under 20 minutes).
  3. Treat gowning and behaviour as part of the contamination control strategy. Slow, deliberate movement is a control measure.
  4. Put monitoring probes where people actually work, not where the cabling is easy.