Before qualification starts, someone has balanced every supply grille in the building: the commissioning engineer.

For graduates wondering what the job involves, here is a normal week.

Most of it is spent system by system. One AHU and the rooms it serves is a package. You walk it against the drawings before anything is energised: dampers, filters, drains, sensor positions, labels. You start the fans with the controls engineer, check rotation and interlocks, then balance airflow room by room until each supply grille delivers its design flow and the pressure cascade settles where the room data sheet says it should.

Then the evidence. Walkdown records, balancing sheets, instrument calibration certificates, a punch list with every item that blocks qualification closed. When the package is turned over, the qualification team runs the cleanroom tests on it: classification, HEPA installed leak test, recovery, smoke study, pressure differentials. If your commissioning was careless, those tests will find out, in front of QA.

It is hands-on, occasionally hot, and more paperwork than people expect. It is also the fastest place to learn how HVAC, controls and validation fit together.

Graduates who join us follow a skills matrix and an Individual Improvement Plan, from junior to senior to lead, with GMP, validation and project management training along the way. Our 12-month internship is one way in.

Careers and internships at Humiley

Related

More on this subject

PADR: how we measure engineer development

Every Humiley engineer has a Performance Appraisal Development Review twice a year, built on their skills matrix and Individual Improvement Plan. It records which competencies moved, the work that shows it and the plan for the next six months, so progression from junior to senior to lead has evidence behind it.

InsightRead

What a quantity surveyor does on a GMP project

A cleanroom panel package can be 90% installed and 0% ready for qualification. On a GMP project the quantity surveyor measures from drawings and BIM, keeps the cost plan and prices variations, and earned value needs a second measure, rooms handed over to qualification, to show a shortfall in time.

InsightRead

Cleanroom HVAC design means load calculations where moisture often outweighs heat, pressure cascades typically 10–15 Pa between grades, coils sized for wet-season dew points, BIM coordination and a paper trail for every airflow. Humiley trains graduates through a skills matrix and a 12-month internship program.

InsightRead