What a quantity surveyor does on a GMP project

  • Careers
  • 1 min read

A cleanroom panel package can be 90% installed and 0% ready for qualification.

On a pharma project the quantity surveyor's monthly report has to show both. Most of a QS's week looks like any construction job: measuring quantities from drawings and the BIM model, holding the cost plan against the approved budget, pricing variations before the work is instructed.

What changes on a GMP plant is the definition of done. A contractor's progress claim usually counts a wall panel once it is fixed and sealed, but the owner needs the room around it closed out: punch list cleared, commissioned and balanced, and handed to qualification with its documents.

Earned value measured only on installed quantities will look healthy right up to the month IQ was due to start. Adding a second measure, rooms handed over to qualification, shows the shortfall while there is still time to move crews and re-sequence the finishing trades.

That monthly report puts cost and earned value next to schedule and risk, which is how Humiley's project management reports are laid out on pharma plants. Quantity surveyors are among the roles we have recruited for on those projects, alongside HVAC, electrical and civil engineers.

Careers and internships at Humiley

Industries

Related

More on this subject

Inside the role: cleanroom HVAC design engineer

Cleanroom HVAC design means load calculations where moisture often outweighs heat, pressure cascades typically 10–15 Pa between grades, coils sized for wet-season dew points, BIM coordination and a paper trail for every airflow. Humiley trains graduates through a skills matrix and a 12-month internship program.

InsightRead

Inside the role: the project administrator

On a PMC pharma project the project administrator keeps the document register: revision, reviewer, due date and status code for every drawing and submittal. Most of the work is checking what arrives against it: an unclouded revision, a Rev C drawing sent after Rev D was issued, comments that never reached the fabricator.

InsightRead