Integrity on a project: report it the day you find it

  • News
  • 1 min read

A clash found on Tuesday and reported on Friday costs the project three days nobody gets back.

The clash itself is usually ordinary. A duct route runs through the sprinkler main, or a vendor drawing arrives late enough to push the FAT. What makes it expensive is the gap between the engineer seeing it and anyone else hearing about it.

That gap is widest early in a career. You found the problem, so you want to arrive with the fix as well, and you sit on it while you work one out. Meanwhile the contractor carries on to the old drawing, and the client's program still shows the old date. By the time the fix is ready the duct may already be hung, and a revised drawing has turned into rework and a variation claim.

We count Integrity among our values, and on a project this is mostly what it looks like. The line we hold to with clients is that we will tell them the honest date rather than the one that wins the work. That promise depends on whoever first sees the slip saying so the same afternoon, with or without a fix in hand.

Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)

Related

More on this subject

A hygienic AHU that passes FAT clean can still reach start-up full of site dust and condensation. Factory-fitted caps, wrapping that sheds rain without trapping moisture, desiccant for shipping, dry covered storage and an internal inspection before the first fan run protect what the FAT proved.

InsightRead