Maintainability is designed on the AHU drawing

  • News
  • 1 min read

If the access zone isn't dimensioned on the AHU general arrangement drawing, someone will fill it with a cable tray.

An AHU is designed once and then maintained for decades. Three routine tasks need space that nobody draws by default:

  1. Bag and HEPA filters have to come out straight, without tilting through a gap narrower than the filter. Side withdrawal or front access decides which side of the unit must stay clear.
  2. Coils slide out sideways for cleaning or replacement, so the pull side needs clear space roughly equal to the coil length. Put that side against a wall and the next coil replacement means opening up the casing.
  3. EC fans in a fan wall come out one at a time through the access door, but only if the door is big enough and there is somewhere to put the fan down. Larger plug fans need a lifting point above them.

On the AHU GA these zones belong as dimensioned volumes, carried into the BIM model, where other trades see them as obstacles instead of empty space.

Related

More on this subject

A single differential gauge across several AHU filter stages cannot say which stage loaded, so teams change everything or guess. A gauge per stage, marked with the commissioning reading and change limit and kept on the calibration list, allows each stage to be changed on condition. BMS transmitters add a trend.