BIM coordination in cleanrooms: issue the void zone by zone

  • News
  • 1 min read

The main supply duct arrives on site. The cable tray is already hanging where the duct was drawn.

The tray was drawn there too, on a different drawing. That is the normal result when HVAC, electrical, clean utilities, fire, structure and architecture each issue their own package and meet for the first time in the ceiling void. Every clash becomes an RFI, a site sketch and a change nobody priced.

A BIM model does not stop that on its own. Six discipline models can sit in one federated file and still be issued on six different dates. What changes the outcome is an issue rule:

  1. The void is split into zones, and each zone has a clash register with an owner and a closing date for every clash.
  2. No discipline issues a zone for construction until that register is closed and each discipline lead has signed it.
  3. Soft clashes count. Filter withdrawal, coil pull space, valve access and pipe slope are modelled as volumes, so they appear in the register like any duct.
  4. Shop drawings are checked against the signed zone, not against whatever drawing each trade received last.

It costs program time at the front. Zones issue a little later, and together.

Do your discipline packages issue on one date per zone, or each on its own?

Related

More on this subject

WFI belongs in the Contamination Control Strategy

EU GMP Annex 1 (2022) gives WFI circulation above 70 °C as an example of minimizing the risk of microbial growth. Keeping a loop hot drives the design: ASME BPE dead legs of L/D ≤ 2, turbulent flow to the last user point, planned sanitization and sensors on the return. The CCS should justify all of it.

InsightRead

Energy measures that change validated cleanroom conditions go through Annex 15 change control. Classification alone can mean 10 sample locations for a 50 m² room, at rest and in operation, before recovery tests and a CCS update. Price that next to the kWh, or design reduced modes in and qualify them once.

InsightRead

Four checks at the basic-design gate

Before detail design opens, a GMP project should have frozen room data sheets and pressure cascade, loads that match the equipment list, a URS for each critical system and owned open items. A cascade change after the ducts are drawn reaches the duct sizes, terminal filters, AHU selection and every neighbouring pressure step.