The date in the tender is the easiest thing in the proposal to promise and the most expensive thing to believe.
This is how an optimistic design date turns into site cost. The design team is oversubscribed, so drawings go out on time with hold clouds on them. The contractor mobilises against the program. Installers reach the holds, stop and raise RFIs. Answers come back as site sketches that nobody coordinated with the other disciplines. Some become rework, some become variations, and the start of qualification moves anyway.
The design deliverable met its date. The project didn't.
The warning signs are visible before award. A team list that looks the same in every proposal. No named reviewer for each discipline. A program where design finishes exactly when procurement needs it, with no float for your own review cycle.
We will tell you the honest date rather than the one that wins the work. Sometimes that means ours is not the fastest program on the table.
Planning a project for next year? Talk to an engineer now: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)