An AHU submittal quoting 5,500 CFM at 250 Pa, against a schedule of 10,000 m³/h at 400 Pa, falls short on both numbers.
At 1.699 m³/h per CFM the airflow is about 9,345 m³/h, 655 m³/h or 6.6% under the schedule. In a cleanroom that comes straight off the air change rate: a room designed for 20 an hour gets about 18.7.
The pressure figure matters more, because nobody can convert it away. 400 Pa is what the ductwork, terminal HEPA filters and dampers were calculated to need. A fan working against 400 Pa instead of 250 moves back along its curve and delivers less than 5,500 CFM, and only the curve for the fan actually offered says how much less.
Speeding the fan up during balancing is the usual site fix, and it is not free. Through the same ductwork, 7% more air needs about 15% more pressure and, by the fan laws, about 23% more fan power. That covers only the unit gap, before the missing static pressure is counted, so whether the motor has that margin is worth knowing now.
The review comment we would send back asks for the operating point at 10,000 m³/h and 400 Pa, with fan speed and absorbed power, read off that curve.
AeroSano units are engineered from the project's own airflow schedule and load calculation, and every unit is FAT-tested and witnessed.
What does your submittal review ask for beside the airflow figure?