Replacing one AHU: why the cascade comes back into OQ

  • News
  • 1 min read

A replacement AHU that supplies 5% more air than the old one can almost double the pressure across a cleanroom door.

Take a room with 2,000 m³/h supply and a flow-controlled return holding 1,800 m³/h. The other 200 m³/h leaks round the door into a corridor served by a different AHU, and the room holds 10 Pa. The new unit delivers 2,100 m³/h, the return stays at 1,800, and leakage becomes 300 m³/h. Door gaps leak roughly as ΔP^0.65, so the differential goes to 10 × 1.5^(1/0.65), about 19 Pa.

Behind a fixed manual damper the return also rises a little as the room pressurises, and rooms on the same AHU gain supply together, so a door between two of them moves less. Both pull the figure below 19 Pa, though not back to the 10 Pa that was qualified.

So requalification after a replacement is a change control decision, argued stage by stage. Annex 15 expects the impact on the qualified state to be assessed and the extent of requalification justified.

  1. DQ, if duty, coil, fan or filter arrangement changed.
  2. IQ, always, for the new unit.
  3. OQ, for airflow, cascade and alarms in every room it serves.
  4. Room requalification: classification, HEPA leak tests where housings were disturbed, recovery if airflow moved.

Where a stage is left out, the change record says why.

We take on single AHU replacements in running facilities as well as greenfield plants.

Related

More on this subject

Periodic and event-driven requalification

A new AHU on a running suite moves the pressure cascade, so its event-driven requalification reaches the differential at every door it serves. Change control sets that scope. Annex 1 (2022) separately caps periodic cleanroom intervals at 6 months for Grade A and B and 12 for C and D.

InsightRead

Periodic requalification: what is retested and how often

EU GMP Annex 1 (2022) sets maximum requalification intervals: 6 months for Grade A and B cleanrooms and 12 months for Grade C and D. Classification, HEPA leak tests, airflow volume, pressure differentials and air velocity, or recovery where airflow is not unidirectional, are retested. A risk assessment can shorten these intervals, never extend them.

InsightRead