A replacement AHU that supplies 5% more air than the old one can almost double the pressure across a cleanroom door.
Take a room with 2,000 m³/h supply and a flow-controlled return holding 1,800 m³/h. The other 200 m³/h leaks round the door into a corridor served by a different AHU, and the room holds 10 Pa. The new unit delivers 2,100 m³/h, the return stays at 1,800, and leakage becomes 300 m³/h. Door gaps leak roughly as ΔP^0.65, so the differential goes to 10 × 1.5^(1/0.65), about 19 Pa.
Behind a fixed manual damper the return also rises a little as the room pressurises, and rooms on the same AHU gain supply together, so a door between two of them moves less. Both pull the figure below 19 Pa, though not back to the 10 Pa that was qualified.
So requalification after a replacement is a change control decision, argued stage by stage. Annex 15 expects the impact on the qualified state to be assessed and the extent of requalification justified.
- DQ, if duty, coil, fan or filter arrangement changed.
- IQ, always, for the new unit.
- OQ, for airflow, cascade and alarms in every room it serves.
- Room requalification: classification, HEPA leak tests where housings were disturbed, recovery if airflow moved.
Where a stage is left out, the change record says why.