Pilot scale for tablets starts at 100,000 units

  • Life Sciences
  • 1 min read

For tablets, pilot scale has a floor of 100,000 units in ICH Q1A(R2), and that floor sets the size of equipment a receiving site needs.

The figure sits in the glossary. A pilot scale batch is made by a procedure fully representative of and simulating full production scale. For solid oral dosage forms it is generally, at a minimum, one-tenth of full production scale or 100,000 tablets or capsules, whichever is the larger.

With a commercial batch of 2,000,000 tablets, one-tenth is 200,000 and that figure applies; at 500,000, one-tenth is only 50,000, so the 100,000 takes over.

Q1A(R2) goes on: stability data should be provided on at least three primary batches of the drug product, and two of the three should be at least pilot scale. The third can be smaller, if justified. A 20,000-tablet development batch can only ever be that third one.

For the plant, the count turns into kilograms. At 500 mg a tablet, 100,000 tablets is 50 kg of blend before losses. A receiving site with a 10 kg laboratory granulator and a production line has nothing in between to make these batches on.

Settle the registration batch size before the equipment list for the transfer is frozen. The glossary says "generally", and the requirements of the target market still have to be read.

Industries

Related

More on this subject

Plug fan or belt drive in a GMP supply AHU

A V-belt sheds rubber dust into the airstream for its whole life, and in a GMP supply AHU that dust loads the final filters. Belt drives also lose a few per cent of shaft power and need regular tensioning. Direct-drive plug fans avoid all three, though a large belt-driven housed fan can still win at high pressure.

InsightRead

PQR: what engineering owes the product quality review

The product quality review is the regular, documented review of each authorised medicinal product, normally annual in the 2013 text of EU GMP Chapter 1; the US rule is 21 CFR 211.180(e). One listed item is the qualification status of equipment and utilities such as HVAC and water, which engineering should keep current through the year.

InsightRead