Hot WFI at 80 °C sends saturated vapour through the tank's vent filter every time the level rises.
If the filter housing sits at plant-room temperature, that vapour condenses in it. The cartridge is hydrophobic, but a film of condensate across the pleats still closes off pores. The filter passes less and less air and looks normal from outside.
Then the loop pumps draw the level down, or cold make-up water enters the hot tank and the vapour in the headspace collapses. Air cannot come in fast enough through a wet cartridge, and the tank goes into vacuum. Many storage tanks are atmospheric vessels with little or no vacuum rating on the datasheet, and a tank can be pulled in like a drinks can.
The remedy is well known. Heat the housing, by steam jacket or electric tracing, so the cartridge stays a few degrees warmer than the water. Size the filter for the fastest inbreathing case, vapour collapse included. And fit vacuum protection that reports: a rupture disc rated for vacuum, with a burst indicator wired to an alarm.
WHO's GMP text on water for pharmaceutical use (TRS 1033, Annex 3) lists hydrophobic, bacteria-retentive vent filters tested for integrity, and bursting discs with external rupture indicators, among the points that should be considered for storage vessels. Heating the housing is design practice for hot tanks.
Talk to an engineer: contact@humiley.com · +84 28 7777 6668 (Viet Nam office)
Industries