A chilled-water pipe at 6 °C in a plant room with a 26 °C dew point will drip unless its outer surface stays above 26 °C.
Insulation thickness on chilled-water lines in Viet Nam is usually sized for condensation first and energy second. Get the energy thickness wrong and you pay a little more for cooling. Get the condensation thickness wrong and water runs along the pipe, soaks the lagging, drips on cable trays and grows mould on the ceiling void.
The calculation is in BS 5422 and ISO 12241. It takes four inputs: the water temperature, the ambient dry-bulb, the ambient dew point and the emissivity of the outer surface. The last one surprises people. Bright aluminium cladding radiates less, so its surface runs colder than a painted or plain finish, and the same pipe needs more insulation under it.
Thickness only works if the vapour barrier is unbroken. Warm humid air finds the gap at a hanger, a valve body, a strainer or a flange left bare for access, and moisture migrates into the insulation from there. Wet insulation insulates badly, so the surface gets colder and the wetting spreads.
On site, the hangers are where we look first: insulated pipe supports with the barrier sealed across them, and removable valve jackets instead of open bodies.