Check whether the air pressure drop on a cooling-coil selection sheet is the wet or the dry figure before the supply fan is selected on it.
A fresh-air coil in Viet Nam condenses for most of the year. Water films on the fins raise the air-side pressure drop, so a fan sized on a dry number runs short of air on the humid days. A sheet rated where the coil does not condense can only give a dry figure, so read the pressure drop together with the entering condition.
That condition should give dry-bulb and wet-bulb together, at the peak dew point case in your design basis; on dry-bulb alone a sheet says little about moisture. The leaving dry-bulb and wet-bulb then fix the leaving dew point, the moisture limit for every room the unit serves, and that is the figure to hold against the room RH specification.
The other lines are quicker. Around 2.5 m/s face velocity, condensate starts to leave the fins with the air and lands in the casing or on the next filter. Water ΔT should match what your chilled-water plant really delivers, often less than the design figure. Deep coils with tight fins dry the air well but are the hardest to clean in a GMP unit.
AHRI 410 covers coil rating; the sheet should state the conditions it was rated at. Our AHU selection platform runs a psychrometric engine for this check against the design basis.
Has a wet pressure drop ever left one of your fans short of airflow?