Restarting AHU fans on a standby generator

  • News
  • 1 min read

Three 30 kW supply fans started direct-on-line at once ask a standby generator for six or more times their running current.

A generator is judged by how far voltage and frequency dip when a block of load lands on it. Too large a step and the voltage sags far enough for contactors to drop out and drives to trip on undervoltage, and the plant restarts twice.

Three things keep the steps small.

  1. Start through drives. A fan on a variable speed drive or an EC motor ramps up and draws little more than its running current. Most cleanroom AHU fans already have drives; check the ones that don't, such as extract fans and pumps.
  2. Stagger the restart. After the transfer switch closes, bring loads on in blocks a few seconds apart. Controls and monitoring first, and they should already be on UPS. Then the AHUs serving the most critical grades, then the rest. Chillers come last, with their own restart delays. Each suite's start order also has to keep its cascade the right way round.
  3. Size for the largest step. Give the generator vendor the load schedule as blocks with their starting kVA, and the transient performance class required under ISO 8528-5. A set chosen on total running kW alone may stall on the first block.

Humiley designs LV–MV power up to 22 kV and cleanroom HVAC in one team, so load blocks and AHU start order sit on the same drawings.

How is the restart sequence on your standby supply tested?

Related

More on this subject

Two envelopes for a cleanroom HVAC tender

Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.

InsightRead

Value engineering after tender: savings that return at OQ

After an over-budget cleanroom HVAC tender, three savings recur: an EN 1886 L2 casing instead of L1, fewer room pressure transmitters, and deleted door drop-seals. Each can reappear as an OQ failure in airflow, alarm testing or pressure differentials, so check every line against its URS requirement and test before accepting it.

InsightRead

Why qualified rooms stay constant volume

A classified room's air change rate, recovery time and pressure steps were proved at one airflow. Constant volume holds each room's flow at that value with a terminal, while the fan speeds up as filters load. VAV moves supply with the cooling load, so it belongs in offices, technical areas and fume-hood exhaust.

InsightRead