"3 bar" pure steam: gauge or absolute

  • News
  • 1 min read

Pure steam quoted at "3 bar" can mean steam that saturates near 144 °C or near 134 °C, and datasheets rarely say which.

The difference is atmospheric pressure, about 1.013 bar. At 3 bar gauge the steam is at about 4 bar absolute and saturates near 144 °C. At 3 bar absolute it saturates near 134 °C. Roughly 10 °C separates two readings of the same line.

For a sterilizer that decides whether the cycle can run. A 134 °C cycle needs saturated steam at about 3.04 bar absolute in the chamber, roughly 2 bar gauge, plus whatever the supply pipework loses on the way. A generator delivering 3 bar gauge has margin to spare. One delivering 3 bar absolute cannot reach the cycle temperature at all, and that shows up at the first OQ run rather than in the bid review.

Instruments carry the same trap. A transmitter ranged 0–6 bar reads gauge or absolute depending on its model code, and swapping one for the other of the same range puts the reading off by about 1 bar on the first day.

The discipline costs nothing. Put a suffix on every pressure in the URS and on every datasheet you issue, bar(g), bar(a), kPa(g), psig or psia, and send a question back whenever a vendor document says only "bar".

PW, WFI and pure steam systems are part of our engineering scope, designed alongside the cleanroom HVAC.

Has a missing g or a ever cost one of your projects an OQ run?

Related

More on this subject

EU GMP Annex 1 (2022) gives WFI circulation above 70 °C as an example of minimizing the risk of microbial growth. Keeping a loop hot drives the design: ASME BPE dead legs of L/D ≤ 2, turbulent flow to the last user point, planned sanitization and sensors on the return. The CCS should justify all of it.

InsightRead

A retention that pays for the turnover file

Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.

InsightRead

Annex 1's scope reaches non-sterile plants

The scope of EU GMP Annex 1 (2022) says some of its principles, including the contamination control strategy, may be used for certain non-sterile products such as liquids, creams and ointments. A semi-solids plant that writes a CCS tying room grades, flows, water and monitoring to product risk has an answer for the inspector.