Particles of 5 µm and larger are the size most easily lost between a Grade A sampling probe and a remote counter.
Heavier particles settle in horizontal runs. In a bend they cannot follow the air round the corner and hit the tube wall. Charged particles stick to a tube that is not conductive. The smaller 0.5 µm particles mostly get through. So the loss is selective, and it falls hardest on the size channel that Annex 1 watches for signs of an intervention or a failing process.
Annex 1 (2022) asks sites to consider tube length and bends in remote sampling systems. In practice that becomes a short list:
- Keep tubes short. Put the counter or the manifold as close to the sampling point as the room allows.
- Use generous bend radii and as few bends as possible. A tight elbow near the probe does the most damage.
- Avoid long horizontal runs, where settling works on every metre.
- Use conductive or static-dissipative tubing.
- Qualify the transport loss for the installed line, with a ≥ 5 µm challenge, and keep the result with the system file.
A counter calibrated perfectly at its inlet still under-reads if the tube in front of it was never tested.
When the EMS is designed with the room, the counter locations and tube routes are drawn together.