Requalification and calibration on one calendar

  • Maintenance Service
  • 1 min read

A room requalified in March with a pressure transmitter that went out of calibration in February has a report that proves very little.

It happens because two schedules have two owners. Requalification usually sits with QA or validation, on the Annex 1 intervals: at most every 6 months for Grade A and B, every 12 months for C and D. Calibration sits with engineering or maintenance, on intervals set instrument by instrument. Each calendar is correct. Nobody reads them together.

The instruments involved are of two kinds. The room's own sensors: differential pressure, temperature, RH, the ones the BMS alarms on. And the test instruments: particle counters, photometers, anemometers, usually calibrated by the test contractor's lab.

One calendar fixes most of it:

Calibrate the room's sensors in the weeks before the requalification, not after.

Check the test instruments' certificate dates as part of pre-test approval, not in the final report.

When a calibration finds a sensor out of tolerance, open an impact assessment on every result it touched since its last good calibration.

That last one is the rule people forget, and the one an inspector will ask about.

Periodic requalification and calibration both sit in our Maintenance Service, and we plan them from the same asset register.

Industries

Related

More on this subject

HVAC changes and the repeat media fill

EU GMP Annex 1 (2022) lists significant modification to the HVAC system among the reasons to repeat an aseptic process simulation. Changes to airflow pattern, pressure regime or filter housings in aseptic areas should reach QA with an engineering note before the work, and the requalification should be planned with the shutdown.