Testing unidirectional and mixed airflow

  • Life Sciences
  • 1 min read

A Grade C room with a high air change rate still cannot protect an open vial.

Mixing lowers the average count; it does not carry a particle away from one point.

Unidirectional airflow does that job, and Annex 1 gives it a guidance speed of 0.36–0.54 m/s at the working position. The speed reading shows the parallel streams are fast and even at the measuring plane. Whether they still sweep past the needle with an operator's arm over the vial, or whether a machine guard or a return grille bends them back, only shows up in the smoke study, and inspectors will ask to watch the film.

For a mixed-flow room the useful number is how fast dilution works. The ISO 14644-3 recovery test raises the particle count and times its fall to one hundredth, the 100:1 recovery time. That result is set against the clean-up period the site has justified for getting back to at-rest limits after operations. A room already inside it gains little from more air changes except fan energy.

The two go wrong in opposite directions. Air changes get added to a mixed-flow room in the hope of protecting open product, and unidirectional ceilings get fitted in a Grade C room where nothing in the process is exposed.

Industries

Related

More on this subject

What ends the life of a HEPA filter

EU GMP Annex 1 (2022) asks for an integrity test of final filters at requalification and puts no age on the filter. A terminal HEPA is replaced when a leak cannot be repaired within site limits, when pressure drop reaches the manufacturer's final value, or after damage or wetting. On glass-fibre media, dust loading alone does not lower efficiency.

InsightRead

As-built classification on a new cleanroom suite

ISO 14644-1 allows a room to be classified as-built: installation complete, services running, no equipment, materials or people. On a new suite it shows whether the HVAC, filters and envelope can reach the class alone. It says nothing about machines or people, so the GMP classification is still done at rest and in operation.

InsightRead

Both states are required; only the stage is a choice

A 50 m² Grade B room needs 10 classification locations under ISO 14644-1:2015, and EU GMP Annex 1 requires them at rest against ISO 5 and in operation against ISO 7, with the smoke study in both states. Whether each run sits in OQ or PQ is for the URS and risk assessment to justify.

InsightRead