ISO 14644-1 defines three occupancy states. Annex 1 grades use two of them, and a new suite reaches the third one first.
As-built means the installation is complete, with all services connected and working, but no production equipment, no materials and no people. It is the state a suite is in after the HVAC is balanced and before the process equipment arrives. Classifying the rooms then is legitimate under ISO 14644-1, and on a new project it is often the most informative test you will run.
An as-built result tells you whether the air handling, the terminal filters and the room envelope can reach the class on their own. If an empty room fails, the fault is in the HVAC, a filter or a leak path, because nothing else is in there to blame. That is far easier to sort out before a filling line is bolted to the floor.
It cannot tell you anything about the equipment. Machines add heat, shed particles, block the supply air and leave dead zones behind their guards. An empty room has none of that. Nor does it say anything about people, who account for most of the difference between at rest and in operation.
As-built therefore belongs in the commissioning or OQ plan as a construction acceptance test. The GMP classification is still done at rest, with the equipment installed and standing by, and then in operation. A report that files the as-built result as the at-rest classification will be questioned.