Most VMPs we review restate the policy well and leave out what an inspector opens them for: the current status of each system.

EU GMP Annex 15, in its 2015 revision, lists what the validation master plan or an equivalent document should cover, at minimum:

  1. The qualification and validation policy.
  2. The organisational structure, with roles and responsibilities.
  3. A summary of the facilities, equipment, systems and processes on site, and their qualification and validation status.
  4. Change control and deviation management for validation.
  5. Guidance on how acceptance criteria are developed.
  6. References to existing documents.
  7. The qualification and validation strategy, including requalification where it applies.

Build item 3 as a table. Every direct-impact system gets a row with its last qualification date, the next requalification date and any open deviation. An inspector can then pick the systems worth a closer look within minutes. A paragraph promising that all systems will be qualified gives them nothing to choose from, so they sample more widely.

Item 5 matters too. If acceptance criteria are set protocol by protocol, two AHUs of the same design can end up tested against different limits.

At Humiley the validation strategy and qualification roadmap are written in parallel with the design, so the VMP system list shares the design basis of the drawings.

Industries

Related

More on this subject

Zero growth and the HVAC record around a media fill

Annex 1 sets zero growth as the APS target, and any contaminated unit fails it. The environmental side of the investigation starts from viable monitoring, with HVAC and EMS trends as support, so review trends before the fill, confirm logging and clock sync, and agree which HVAC events count as interruptions.

InsightRead

A month-end note from Tony Nguyen, CEO

After more than twenty years with automation vendors and running an EU-GMP EPC contractor, Tony Nguyen saw problems start at the handovers between companies rather than inside any one scope. This note explains why Humiley is organized as one accountable team across design, project management, equipment and maintenance.

InsightRead

The revised EU GMP Annex 1 has applied since 25 August 2023, with point 8.123 following in 2024. A site still planning its gap assessment is years behind. Most findings land in the CCS, for example a pressure alarm delay set at commissioning that nobody can justify.

InsightRead