45 mmAq and 50 m³/min on the fan datasheet. 450 Pa and 3,000 m³/h on the schedule. Close, but not yet the same.
Cleanroom projects in Viet Nam often mix European standards, US equipment data and Asian vendor datasheets, and fan data is where the units drift furthest apart. Two conversions cover most of it:
1 mmAq (millimetre of water) is about 9.81 Pa, so 45 mmAq is about 441 Pa.
1 m³/min is 60 m³/h, so 50 m³/min is 3,000 m³/h.
The airflow matches. The pressure is 9 Pa short, about 2%, which on its own may sit inside the fan's tolerance.
The bigger question is what the pressure means. A schedule usually states external static pressure: what the fan has left for ductwork, terminal filters and dampers after the unit's own coil, filters and casing. Some datasheets give total or fan static pressure instead, before those internal losses. Read that way, the coil and filter losses still have to come off the 441 Pa before the ductwork sees any of it.
Ask the vendor to restate the offer in the schedule's units and on the schedule's pressure basis, with the fan curve at the duty point.