The last page of a qualification report should let someone who never saw the tests decide whether the system moves on.
Many are just the executed protocol with a cover sheet, three hundred pages of ticks and signatures, and a final line reading "OQ completed". The reader still has to work out whether it passed, what went wrong along the way, and who agreed it could proceed.
EU GMP Annex 15 asks the report to cross-reference the protocol, summarise the results, comment on deviations, draw conclusions, and formally release the system for the next step. In practice the summary should cover:
- Which protocol, which version, and which system boundary it covered.
- The results against each acceptance criterion, in a table a reader can scan.
- Every deviation, its root cause, and what it did to the result. Closed, or carried forward with a justification and an owner.
- A conclusion in plain words: fit for the next stage, fit with conditions, or not fit, with any conditions listed.
- The release, signed and dated by the responsible personnel your quality system names, before the next protocol is executed.
Writing "fit with conditions" commits the author to listing the conditions and giving each one an owner, which is why so many summaries settle for "completed".