Maintenance fits a new damper actuator in place of a failed one, and the record is closed as a CAPA. No cause was removed.
Three terms get used as one. ISO 9000 defines them separately.
A correction eliminates the nonconformity that was found. The new actuator is a correction, and the damper works again.
Corrective action goes after the cause, so that the failure does not come back. Someone has to ask why the actuator failed. Suppose condensate was dripping onto it from an uninsulated chilled water valve above. Insulating that valve is the corrective action.
Preventive action removes the cause of something that has not happened yet. If the same valve detail sits above actuators on six other air handling units where nothing has failed, fixing those is preventive. Replacing the failed part is neither of the two.
A record that stops at the correction is usually opened again, under a new number, the next time the actuator dies.
ICH Q10 section 3.2.2 says a company should have a CAPA system fed by complaints, non-conformances, deviations, audits, inspection findings and trends, with the effort of the investigation matched to the level of risk. EU GMP Chapter 1 adds that the effectiveness of the actions should be monitored and assessed. On a form, that comes down to an owner, a date and a check that it worked, for each action.
"Root cause: actuator failure" is a common entry. It names the event and leaves the cause blank.