What a higher pressure cascade costs in leakage air

  • Life Sciences
  • 1 min read

Going from 10 to 20 Pa across a cleanroom door adds about 41% to the air leaking through its gaps, and real cracks leak closer to 57% more.

The 41% comes from the orifice equation, Q = Cd·A·√(2ΔP/ρ). Flow through door gaps, cable penetrations and panel joints rises with the square root of pressure, so doubling ΔP gives √2, about 1.41 times the leakage.

Narrow cracks add friction that a sharp-edged opening does not have, and measured building leakage fits a flow exponent nearer 0.65 than 0.5. With n = 0.65, 2^0.65 ≈ 1.57.

The extra air leaves the room as treated supply, already cooled and dried for a tropical climate and filtered at the terminal, and the AHU has to make it up. On a long cascade the step repeats at every door.

Annex 1 guidance asks for at least 10 Pa between adjacent grades, and 10–15 Pa is the usual design range. Some rooms do justify more. A containment suite may need a bigger step, and so may a room where transducer tolerance takes a good part of a 10 Pa margin. Write that reason into the design basis next to the number. Setting 20 or 30 Pa because higher feels safer mostly buys leakage air and heavier doors.

We set cascade values from the room data sheets and a leakage estimate, and argue them in the CCS.

More on our news page

Industries

Related

More on this subject

Periodic requalification: what is retested and how often

EU GMP Annex 1 (2022) sets maximum requalification intervals: 6 months for Grade A and B cleanrooms and 12 months for Grade C and D. Classification, HEPA leak tests, airflow volume, pressure differentials and air velocity, or recovery where airflow is not unidirectional, are retested. A risk assessment can shorten these intervals, never extend them.

InsightRead

Three APS runs across all shifts, and the HVAC has to hold still

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead