Why a drain pan needs paperwork

  • Manufacturing & Distribution
  • 1 min read

A stainless steel drain pan with no passivation record is a question at IQ, and nobody on site can answer it.

Welding a stainless pan or a coil frame leaves heat tint and a chromium-depleted layer under it, which is where corrosion starts. The tint has to come off first, by pickling or mechanical cleaning. Passivation, usually an acid treatment to a procedure based on ASTM A380 or A967, then allows the chromium oxide layer to re-form. A part that was done well looks exactly like one that was never treated, so after delivery you cannot inspect your way to the answer.

The evidence has to be made at the time. For each passivated part that means the procedure used, the chemical and its concentration, the contact time, the date, who did it, and the check afterwards. Welds need their own records: the welder, the procedure, and a visual inspection result.

By the time an AHU reaches site, the people who did that work are on the next job. Without the record, the IQ reviewer is left with a deviation, or with retesting the part to ASTM A967 on site, and neither is welcome in week one of qualification.

That is why the equipment file is built during production rather than after FAT. Material certificates, weld and passivation records, the FAT report, O&M and spares go into one file as the unit is made, so IQ starts from a complete record.

AeroSano hygienic air handling units and the equipment file

Related

More on this subject

A retention that pays for the turnover file

Most of a cleanroom HVAC contract is paid before the turnover documents exist. Split the retention into two parts, released on acceptance of the turnover package and of the documents, and size the documentation part on what it would cost the owner to finish as-builts, calibrations and retests without the contractor.

InsightRead

Engineering Solution & Consultancy

Five things a package needs before IQ

IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.

InsightRead