Transfer the analytical methods before the first batch needs them

  • Life Sciences
  • 1 min read

Validation batch one sits in quarantine while the laboratory that has to test it finishes the method transfer.

On a transfer plan the analytical methods tend to sit at the bottom. The laboratory work looks like something that can run alongside the equipment and the batch record. Then the batch is made and its samples start their own clock: hold times, stability time zero.

Annex 4 of WHO TRS 1044, the guideline on technology transfer, gives the order in one sentence. Analytical procedures used to test pharmaceutical products, starting materials, packaging components and, where applicable, cleaning residue samples should be implemented at the testing laboratory before the samples for process validation studies are tested there.

Cleaning samples are in that sentence, and they are the ones left off the list. The first swabs after the first batch need a residue method that already works in the receiving laboratory.

"Implemented" covers more than a signed report. The same guideline says the receiving unit should have the necessary quality control equipment available and qualified at its site, and adequately trained and experienced people in place for the testing. A new HPLC delivered in the same month as the validation batch is on the critical path.

On the project plan, give every method its own line, with a need-by date taken from the first batch that depends on it.

Industries

Related

More on this subject

Knowledge management in ICH Q10, in plain terms

ICH Q10 names knowledge management as one of two enablers of the pharmaceutical quality system: a systematic approach to acquiring, analysing, storing and disseminating information about products, processes and components. In a technology transfer, that means handing over the reason behind each parameter, along with the batch record.