A purified water system is not qualified on handover day. Under WHO guidance, the last phase of its qualification runs for a full year.
WHO guidance on water for pharmaceutical use describes three phases. Phase 1 lasts at least 2 weeks of intensive sampling, typically every day at every point, while operating ranges and cleaning and sanitization procedures are set. Phase 2 follows under the approved operating procedures, to show the system holds within range. Phase 3 covers one year, with routine sampling, to show the system performs through seasonal change in feedwater quality.
The third phase is the one project schedules forget. Production can often begin after phase 2, with water released on the basis of results, but the system is still under qualification. If a seasonal shift in feedwater, a hot month in the loop or a change in usage shows up in the data, it belongs to the qualification record, not just the monitoring log.
Two practical points follow. Sampling points, lab capacity and trending tools need to be in place for a year, not for the first month. And the design has to make that year easy: sample valves at every use point and return, drainable legs, and a loop that can be sanitized without heroics.
We plan the water system's qualification with its design, so the year is on the schedule from the start.