Water qualification takes a year, not a handover

  • Life Sciences
  • 1 min read

A purified water system is not qualified on handover day. Under WHO guidance, the last phase of its qualification runs for a full year.

WHO guidance on water for pharmaceutical use describes three phases. Phase 1 lasts at least 2 weeks of intensive sampling, typically every day at every point, while operating ranges and cleaning and sanitization procedures are set. Phase 2 follows under the approved operating procedures, to show the system holds within range. Phase 3 covers one year, with routine sampling, to show the system performs through seasonal change in feedwater quality.

The third phase is the one project schedules forget. Production can often begin after phase 2, with water released on the basis of results, but the system is still under qualification. If a seasonal shift in feedwater, a hot month in the loop or a change in usage shows up in the data, it belongs to the qualification record, not just the monitoring log.

Two practical points follow. Sampling points, lab capacity and trending tools need to be in place for a year, not for the first month. And the design has to make that year easy: sample valves at every use point and return, drainable legs, and a loop that can be sanitized without heroics.

We plan the water system's qualification with its design, so the year is on the schedule from the start.

More on our news page

Industries

Related

More on this subject

Knowledge management in ICH Q10, in plain terms

ICH Q10 names knowledge management as one of two enablers of the pharmaceutical quality system: a systematic approach to acquiring, analysing, storing and disseminating information about products, processes and components. In a technology transfer, that means handing over the reason behind each parameter, along with the batch record.

InsightRead

Scale-up is more than a bigger batch size

Five times the batch at the same set-points gives different granules, because some parameters depend on scale. WHO's technology transfer guideline says batch sizes should be compared and the impact assessed where they differ. Compare the equipment, check dust, exhaust and water at the new scale, and settle set-points with trial batches.

InsightRead