At 3 a.m. during an aseptic fill, the environmental monitoring server stops logging, and nobody from IT is on site until morning.
EU GMP Annex 11 (2011), clause 16, asks for business continuity: provisions for systems that support critical processes in the event of a breakdown, with the time needed to bring alternatives into use based on risk, and the arrangements documented and tested. For an EMS, the people who carry out those arrangements are the operators and the shift supervisor.
A plan they can use answers four questions.
- Do the particle counters and pressure sensors buffer data locally, for how long, and does the buffer back-fill the database when the server returns?
- Who takes manual readings, from which local displays, on which form, and how often?
- How long may the fill run without continuous monitoring before someone decides to stop, and who is that person?
- What is the target time to restore the server or switch to a standby, and when was it last tested?
The buffering question is the one most often answered from memory. Check it on the actual counters with a planned disconnect, and file what came back.
If you are writing the URS for a new monitoring system, put that disconnect test in it so the OQ protocol has something to execute. Humiley designs automation and SCADA to Annex 11 and 21 CFR Part 11, with the URS written alongside the design.