Sign the DQ section before the purchase order

  • News
  • 1 min read

The URS asked for EN 1886 casing leakage class L1. The AHU was ordered as L2 before DQ was signed, and nobody saw it until IQ.

DQ sits between the URS and IQ in the V-model: the documented check that the design meets the user requirements. On many projects it is written once, as a single report at the end of detail design. Procurement runs to a different date. Long-lead AHUs and dehumidifiers are ordered while the design is still moving, so they can be in fabrication before anyone has read their datasheets against the URS.

By IQ the L2 casing has been built and tested at the factory against the order it was given. Correcting it now means a deviation and change control on the owner's side, and a commercial discussion with a supplier who did what the purchase order said.

We would split DQ along the procurement packages. Before a long-lead item is released, its DQ section is reviewed and signed against the datasheet and drawings at their current revision. The final DQ report then compiles those signed sections and covers what remains of the design.

On Humiley projects the URS, validation strategy and qualification roadmap are written in parallel with the design, which is what makes an early DQ section possible.

Related

More on this subject

Before changing an inherited facility or design, a written gap assessment against the URS and target regulations gives management and inspectors the same picture: evidence from documents and spot measurements, findings graded by risk, and the fix, cost range and schedule impact of each, plus what can stay.