300 TR and 1,000 kW can sit side by side on a chiller bid sheet as if they were the same size of machine.
One ton of refrigeration is 12,000 Btu/h, about 3.517 kW. So 300 TR is roughly 1,055 kW, and 1,000 kW is about 284 TR. The gap is around 55 kW, a little under 6% of the smaller machine. On a load calculated with a 5% margin, the smaller offer has used all of it before the first tube fouls.
Converting fixes the unit. The two figures still may not describe the same duty.
A chiller's capacity holds only at the conditions it was rated at: leaving chilled-water temperature, water flow, and condenser water or outdoor air temperature. A machine rated at 7 °C leaving water gives less when the dehumidifying coils call for 5 °C. An air-cooled unit rated at 35 °C outdoor air gives less on a hotter afternoon on the roof. Ask every vendor for capacity and input power at your design conditions, in kW, in one table, and compare efficiency on one basis, kW/TR for all or COP for all.
Putting both units and the rating conditions into the chiller schedule before it goes to tender means the conversion is done once, by the designer. Selecting equipment against the calculated load at design stage is part of the design-to-procurement handover we manage.